Shell Elapsed time

I there such a utility which will display the elapsed time between two times, eg:-
Code:
Script started on Fri May 24 14:51:46 2019
Script done on Sun May 26 00:54:45 2019
 
To may knowledge the answer to your question is no.
However, a little script can take care of the process for you.

Code:
#!/usr/bin/env perl6

my %months = (
  Jan => '01',
  Feb => '02',
  Mar => '03',
  Apr => '04',
  May => '05',
  Jun => '06',
  Jul => '07',
  Aug => '08',
  Sep => '09',
  Oct => '10',
  Nov => '11',
  Dec => '12',
);

sub MAIN($str1, $str2)
{
        my @parts1 = $str1.split(' ');
        my @parts2 = $str2.split(' ');
        my $date1 = DateTime.new(sprintf("%u-%02u-%02uT%s+00:00", @parts1[3], %months{@parts1[0]}, @parts1[1], @parts1[2]));
        my $date2 = DateTime.new(sprintf("%u-%02u-%02uT%s+00:00", @parts2[3], %months{@parts2[0]}, @parts2[1], @parts2[2]));
        say $date2 - $date1;
}

Then just:

Code:
# ./blah.pl6 'May 24 14:51:46 2019' 'May 26 00:54:45 2019'
122579

I've chosen perl6 to do this but any language is capable of getting the duration between two dates.
 
I'm using a very simple approach:
Get Start and End time in seconds by running:
Code:
date +%s
Then you can easily calculate the difference:
Code:
START=`date +%s`
END=`date +%s`
DELTA=$(( END-START ))
echo $START $END $DELTA
1559147114 1559167743 20629
...and convert the result to HH:MM:SS:
Code:
HOURS=$(( DELTA/3600 ))
MIN=$(( (DELTA-HOURS*3600)/60 ))
SEC=$(( DELTA-HOURS*3600-MIN*60 ))
echo $HOURS:$MIN:$SEC
5:43:49
If needed, you can convert the time in seconds back to normal:
Code:
date -r $END
Wed May 29 16:09:03 MDT 2019
 
I'm using a very simple approach:
Get Start and End time in seconds by running:
Code:
date +%s

That's the sort of answer I like :) ... It prompted me into looking what date() was capable of and I found that GNU date could do something like date --date='Fri May 24 14:15:46 2019' +%s which returns 1558703746. But Freebsd can't do this. Fortunately you can install sysutils/coreutils which installs date as gdate.

Now to come up with a script to show the elapsed time between the start and finish time...
 
But Freebsd can't do this.
Really? The man page date(1) has even an example of such usage. Perfectly works here:
Code:
date -j -f "%a %b %d %T %Y" 'Sat Jun 01 07:02:31 2019' "+%s"
Also, if the start and end strings are provided by a script, isn't it easier to change to seconds at the first place?
 
I hadn't spotted that, but as a result of your post, I've managed to come up with:-
echo `date -j -f "%a %b %d %T %Y" 'Sun May 26 00:54:45 2019' "+%s"` - `date -j -f "%a %b %d %T %Y" 'Fri May 24 13:51:46 2019' "+%s"` | bc

This comes up with 126179, although I'd rather show the answer in hours, but haven't worked out how to apply the rules of precedence in this case... I know that I need to insert brackets if I want to use '/ 3600' at the end, but getting the syntax right is proving difficult.
 
If you use the Korn shell (shells/ksh93) (not sure about other shells), you can put these commands in a script:

Code:
$ (( start = SECONDS ))
$ print $start
33.053455114364624
$ (( elapsed = SECONDS - start ))
$ print $elapsed
23.5835580825805664
 